Use an actual layout for each room and for the route between them. Record the machine’s transport envelope including the approved moving arrangement. Identify which connections, cleaning conditions and operating checks apply at each destination.
Compare the two rooms before quoting
| Check | Room A | Room B |
|---|---|---|
| Smallest confirmed straight opening | 1,120 mm, geometric difference of +70 mm with a 1,050 mm moving envelope. | 980 mm, geometric difference of −70 mm with the same envelope. |
| Utility and interfaces | Record connection reference and approved shutdown or isolation process. | Confirm independent connections and the operating state on arrival. |
| Return and restart | Record approved setup and verification after the move. | Define who confirms the format, condition and first accepted product. |
Escalate the physical interference first
In the example Room B cannot use that opening with the stated moving configuration. Ask the authorised site team to review an alternate route or envelope. Room A’s clearance still needs a handling and tolerance assessment.
If both rooms are feasible, document planned transfer frequency, actual operating conditions and restoration responsibilities. Ask for the offer to cover both setups, including parts that are held in only one room.
Review the equipment scope choices for a stand-alone machine
Share the two-room portable bottling brief with the marked route, moving arrangement and room utility drawings.